Concept masterplan

The Iwokiri Gateway.

A working marine gateway beside Onne, a riverside town, a leaf-shaped marina, and three quarters of the land kept as mangrove. Built in five phases, on land that is leased, never sold.

573 ha
plan area
123 ha
built or raised
75%
of land kept as mangrove
730 m
working quay

Concept illustration

Films

See the plan in motion.

Flythrough of the Gateway · 42 s · narrated

Life at the Fronds

29 s · narrated. Homes, walks, parks and the harbour of the leaf-shaped marina, Phase 4.

The site plan, zone by zone

33 s · music only. Each zone lights up on satellite imagery of the site.

Iwokiri in 23 seconds

23 s · narrated, with captions. Where it is and what it could become.

Concept films made from AI-generated illustrations and satellite imagery, with AI narration and music. Not the real site, not surveyed. Not an offer of investment.

The plan

Twelve zones, one shoreline.

Drawn on the real satellite image of Iwokiri. Hover or tap a number to see each zone.

FHM✦123456789101112↖ Onne port · 3.4 kmBolo Town · 5.7 km →Bonny River estuaryBolo creekN0250500 m
Concept vision · not surveyed
F Water-taxi terminalH Iwokiri Point hotelM Marina entrance✦ HelipadDashed blue: dredged approach channel · white: bridge and roads

In pictures

How it could feel.

The Fronds marina, concept illustration
The Fronds marinaConcept illustration
Iwokiri Marine Gateway, concept illustration
Iwokiri Marine GatewayConcept illustration
Riverside promenade, concept illustration
Riverside promenadeConcept illustration
Maritime and Blue Economy Academy, concept illustration
Maritime and Blue Economy AcademyConcept illustration
Bolo Link Road over the mangrove, concept illustration
Bolo Link Road over the mangroveConcept illustration

Phasing

Ambitious in scale. Strict in order.

Each phase starts only when the one before it is working. The quay waits for a signed tenant; the marina waits for a working town.

  1. Phase 0 · Years 0–2

    In progress

    Prove the site

    • Bathymetric and LiDAR survey, soil borings and a flood study
    • Full environmental and social impact assessment
    • Community Trust, title and consent from every land-holding family
    • Channel and berth design agreed with NPA and NIWA
  2. Phase 1 · Years 1–4

    Planned

    Blue economy and access

    • Fishers' Harbour and Seafood Hub
    • Mangrove Institute, nursery and restoration
    • Water-taxi terminal and energy hub pilot
  3. Phase 2 · Years 3–8

    Planned

    The Marine Gateway

    • Quay reclamation and approach channel, once an anchor tenant signs
    • Logistics, Energy and Free-Zone Park, first plots
    • Onne Link Bridge
  4. Phase 3 · Years 6–12

    Planned

    Town and Academy

    • Iwokiri Town: homes, market, school, clinic
    • Maritime and Blue Economy Academy
    • Bolo Link Road, elevated over the mangrove
  5. Phase 4 · Years 10–20

    Planned

    The Fronds

    • Marina lagoon dredged from degraded marsh
    • Residential islands, waterfront hotels and promenade
    • Opened only when the town and gateway are working

Dredging and reclamation

Building on a mangrove coast, the right way.

32 ha
reclaimed from shoals and marsh
5–7 M m³
fill, indicative
4–6 M m³
dredging, indicative
53 ha
tidal marina lagoon

Order-of-magnitude estimates from the drawn areas, before any survey. For scale, Palm Jumeirah used about 94 million m³ of sand.

What the site data shows

Two kinds of buildable ground

Satellite imagery shows intertidal shoals along Iwokiri's river bank and sparser, degraded marsh inland. The plan reclaims and raises on these first, and keeps the dense mangrove.

Clear of Onne's shipping lane

Iwokiri faces the eastern arm of the estuary, opposite the tip of the Onne peninsula. The Onne fairway appears to run west of that tip, so the Gateway needs its own dredged approach channel. To be confirmed against Admiralty chart BA 3286.

Satellite heights are not ground heights

Public elevation data (SRTM) reads 4–9 m over the site, but in mangrove it measures the tree canopy. Real ground levels need a LiDAR survey before any design.

Channel depth sets the market

Onne's controlling depth is reported at about 10.6–11.4 m. Offshore-support and marine-service vessels work at far less, which suits a Gateway at Iwokiri.

How it would be built

  • Cut and fill in balance where possible: material from the channel and lagoon builds the islands and platforms.
  • Silt is not structural fill, so clean sand comes from licensed Bonny River borrow areas, as at Onne.
  • Soft ground is consolidated with vertical drains and surcharge, with settlement monitored, before anything is built.
  • Platforms are raised above a 1-in-100-year flood plus sea-level rise, set by the flood study.
  • Rock and living-shoreline edges: revetments where ships berth, planted mangrove fringes everywhere else.
  • The lagoon is open to the tide at its entrance so the water exchanges and stays clean.

Approvals it needs

Environmental Impact Assessment Act
Mandatory full study: reclamation, mangrove conversion and housing of 50 ha or more all qualify.
NIWA
Dredging, reclamation and right-of-way permits on inland waterways.
Nigerian Ports Authority
Private jetty and quay approval through its standing committee.
Land Use Act
Statutory title and Governor's consent for every lease.
IFC Performance Standard 6
International lenders require avoiding dense mangrove, no net loss, and net gain in critical habitat.

Sources: NESREA: EIA Act · NIWA · IFC PS6 · ThisDay: Onne depth · NPA pilotage

Every boundary here waits for survey, soil tests and the impact assessment in Phase 0.